Hi David,
Thanks for the suggestion. One thing you might be able to do instead is to use a custom Excel report. I haven't tried this myself, but in theory you should be able to create a report that outputs the equivalent what export to Project Export does. For the conversions of priority, and complexity to MS Project equivalents, you could use an Excel formula (IF statement) to do the conversions in the report template itself. It would take a bit of work, but thought I'd at least mention it as a possible workaround.